Processing - Development Timelines
Development Timelines | Construction Schedule
(All capital costs are current estimates)2003
- Established Project Office
- Constructed office/warehouse building at Argentia
- Began operation of mini-pilot plant at Sheridan Park in Ontario
- Commenced detailed engineering for site preparation
- Installed fiber optic connection
2003-04
- Continued upgrade/replacement of utility services at Argentia
- Earthworks completed construction at Demonstration Plant
- Constructed Demonstration Plant Building
2005
- Installed mechanical, piping and electrical controls
- Installed process equipment
- Commissioned demonstration plant
- Began testing nickel concentrate
2006-08
- Operate demonstration plant
- Complete Environmental Assessment
2008
- Complete feasibility study for commercial processing facility
- Decision to construct either a commercial scale hydromet plant, or a conventional processing facility with the same capacity using proven technology to produce finished nickel
2009 – 2011
- Construction of US$2.2 billion 110-million pounds of nickel per annum hydrometallurgical nickel matte processing facility, or construction of 110-million pound per annum refinery that will produce finished nickel
- Commencement of commercial processing