Skip over navigation

Processing - Development Timelines

Development Timelines   |   Construction Schedule

(All capital costs are current estimates)

2003

  • Established Project Office
  • Constructed office/warehouse building at Argentia
  • Began operation of mini-pilot plant at Sheridan Park in Ontario
  • Commenced detailed engineering for site preparation
  • Installed fiber optic connection

2003-04

  • Continued upgrade/replacement of utility services at Argentia
  • Earthworks completed construction at Demonstration Plant
  • Constructed Demonstration Plant Building

2005

  • Installed mechanical, piping and electrical controls
  • Installed process equipment
  • Commissioned demonstration plant
  • Began testing nickel concentrate

2006-08

  • Operate demonstration plant
  • Complete Environmental Assessment

2008

  • Complete feasibility study for commercial processing facility
  • Decision to construct either a commercial scale hydromet plant, or a conventional processing facility with the same capacity using proven technology to produce finished nickel

2009 – 2011

  • Construction of US$2.2 billion 110-million pounds of nickel per annum hydrometallurgical nickel matte processing facility, or construction of 110-million pound per annum refinery that will produce finished nickel
  • Commencement of commercial processing