Mine and Concentrator:
- Completed construction of concentrator building
- Began construction of permanent accommodations and services complex
- Began pre-stripping the Ovoid
- Installed main power plant
- Commenced installation of mechanical, electrical, piping and control systems
- At year end construction was 74% complete
Hydromet Demonstration Plant
- Completed detailed engineering for hydromet demonstration plant at Argentia
- Negotiated collective agreement with the Resource
Development Council that ensures residents of the local
area have priority for employment at the construction
site
- Built and enclosed the process building
- Upgraded water and sewer infrastructure
- Constructed sewage treatment plant
- Began installing mechanical, electrical, piping and instrumentation control systems
- Began construction of residue storage ponds and fire and process water pumphouse
Innovation Centre
- Completed demolition and installation of foundations and structural steel
- Awarded general contract for architectural, mechanical and electrical systems and interior fit-up to Marco Services Limited
- Completed 80% construction by year-end
|
|